Sanitary Sewer Project Update
- NO WORK
- Area 4 Along Helen St
- Area 4 Along Helen St
- Area 4 Along 4th Ave
- Area 3 Along 6th Ave through the parking lot
- Area 1 Along Gerald Ave, approximately halfway between Shawneee and Mohawk.
A reminder there is no work scheduled for today (1/20).
The remaining sanitary sewer lining operations are outlined below. Please read the tentative schedule below carefully, and as always, the timeline below is subject to change. Updates to the schedule will be provided as soon as possible.
Monday (1/23)
Tuesday (1/24)
Wednesday (1/25)
Thursday (1/26)
Friday (1/27)
Monday (1/30)
The lining installation will normally be completed within an 8 – 12 hour period. Further notice will be given to you 24 – 48 hours in advance with a specific date and time of the liner installation. This notice will be a pink door hanger/flyer. For further explanation of the lining process, and recommendations for residents to follow, please visit the City’s website: Sewer Pipe Odors | North St. Paul, MN (northstpaul.org)
The attached PDF titled “SanitaryLiningProject” is the map that illustrates the location of each area, attached for your reference.