Postponed Roadwork Until December 8, 2025
The previous notification for milling and paving in your area has been revised due to the weather. The Borough and Boswell will be closely monitoring the forecast and will provide a follow-up notification if there are any changes to the above schedule.
From Monday, December 8, 2025, - Wednesday, December 10, 2025 (weather permitting), construction will commence on the above-referenced project. Milling, base repairs, leveling, and paving will occur in the following sequence:
- Monday, December 8, 2025 - Milling, Base Repairs
- Tuesday, December 9, 2025 - Paving
- Wednesday, December 10, 2025 - Paving (If delayed due to weather)
For scheduling related questions, please contact the contractor, Reivax Contracting Corp. at (908)-864-4253. If you have any questions or specific concerns, please contact Ms. Calista Quiatchon of Boswell, Inc. at (201)-334-3045.