West Lebanon, NH - South Main Street Dry Bridge Project Update - Week of November 9, 2026
West Lebanon, NH South Main Street Dry Bridge Project Update - Week of November 9, 2026
During the upcoming week, the contractor will continue installing sheet piles for the cofferdams. On Tuesday, November 10, 2026, crews will pave the base layer for the southern bridge approach. In addition, the large concrete pour (362 cubic yards) for one of the new bridge abutments remains scheduled for the early morning of Thursday, November 12, 2026. Preparatory activities will begin at approximately 5:00 AM and will include construction vehicle movements and the use of work lights. The concrete placement is scheduled to begin at 6:00 AM.
A reminder regarding the footbridge: for everyone’s safety, bicyclists are encouraged to dismount and walk their bicycles across the structure. A designated detour for motorists remains in place.
All area businesses and facilities remain open.
Please be advised that construction crews and vehicles will continue to be active in the area while road work is underway. Although the Dry Bridge will be closed, motorists traveling near the construction zone should proceed with caution as construction activities continue.
For more information about this project, please visit LebanonNH.gov/DryBridge.
During the upcoming week, the contractor will continue installing sheet piles for the cofferdams. On Tuesday, November 10, 2026, crews will pave the base layer for the southern bridge approach. In addition, the large concrete pour (362 cubic yards) for one of the new bridge abutments remains scheduled for the early morning of Thursday, November 12, 2026. Preparatory activities will begin at approximately 5:00 AM and will include construction vehicle movements and the use of work lights. The concrete placement is scheduled to begin at 6:00 AM.
A reminder regarding the footbridge: for everyone’s safety, bicyclists are encouraged to dismount and walk their bicycles across the structure. A designated detour for motorists remains in place.
All area businesses and facilities remain open.
Please be advised that construction crews and vehicles will continue to be active in the area while road work is underway. Although the Dry Bridge will be closed, motorists traveling near the construction zone should proceed with caution as construction activities continue.
For more information about this project, please visit LebanonNH.gov/DryBridge.