Lebanon, NH South Main Street Dry Bridge - Week of September 7, 2026
Lebanon, NH South Main Street Dry Bridge - Week of September 7, 2026
The contractor will continue installing sheet piles for the cofferdams and will complete the construction of the retaining wall. In addition, the contractor will finish building the temporary pedestrian bridge, which will be ready for use when the Dry Bridge closes on Monday, September 14, 2026, at 7:00 AM. At this time, the Dry Bridge remains open to both vehicles and pedestrians.
Utility relocation work is also in progress and is expected to continue for several weeks.
As a reminder, while road work is underway, construction crews and vehicles will be active in the area. Two-way traffic will be maintained whenever possible; however, motorists should anticipate periodic delays. Please exercise caution when traveling through the work zone and follow all posted signs and the instructions of flaggers.
For more information about this project, please visit LebanonNH.gov/DryBridge.
The contractor will continue installing sheet piles for the cofferdams and will complete the construction of the retaining wall. In addition, the contractor will finish building the temporary pedestrian bridge, which will be ready for use when the Dry Bridge closes on Monday, September 14, 2026, at 7:00 AM. At this time, the Dry Bridge remains open to both vehicles and pedestrians.
Utility relocation work is also in progress and is expected to continue for several weeks.
As a reminder, while road work is underway, construction crews and vehicles will be active in the area. Two-way traffic will be maintained whenever possible; however, motorists should anticipate periodic delays. Please exercise caution when traveling through the work zone and follow all posted signs and the instructions of flaggers.
For more information about this project, please visit LebanonNH.gov/DryBridge.