West Lebanon, NH South Main Street Dry Bridge Project Update - Week of July 27, 2026
West Lebanon, NH South Main Street Dry Bridge Project Update - Week of July 27, 2026
Retaining wall construction and sheet pile work are currently in progress and are expected to continue during the week of July 27, 2026. Following completion of the aforementioned work, the pedestrian bridge superstructure work will proceed.
Utility relocations are also underway and will continue for several weeks.
As a reminder, while road work continues, construction crews and vehicles will be present in the area. Two-way traffic will be maintained whenever possible, but motorists should expect periodic delays. The bridge remains open to both vehicles and pedestrians at this time. Please use caution when traveling through the work zone and follow all posted signs and the direction of flaggers.
For more information about this project, please visit LebanonNH.gov/DryBridge.
Retaining wall construction and sheet pile work are currently in progress and are expected to continue during the week of July 27, 2026. Following completion of the aforementioned work, the pedestrian bridge superstructure work will proceed.
Utility relocations are also underway and will continue for several weeks.
As a reminder, while road work continues, construction crews and vehicles will be present in the area. Two-way traffic will be maintained whenever possible, but motorists should expect periodic delays. The bridge remains open to both vehicles and pedestrians at this time. Please use caution when traveling through the work zone and follow all posted signs and the direction of flaggers.
For more information about this project, please visit LebanonNH.gov/DryBridge.