West Lebanon, NH South Main Street Dry Bridge Project Update - May 22, 2026
West Lebanon, NH South Main Street Dry Bridge Project Update - May 22, 2026
Construction of the access road to pavement subgrade is complete, and preparation of the Route 12A subgrade is complete (south approach roadway widened area). Utility relocations are ongoing and will continue for several weeks.
During the week of May 25, 2026, construction crews will continue sewer work and retaining wall work at the Seminary Hill intersection.
As a reminder, while road work continues, construction crews and vehicles will be present in the area. Two-way traffic will be maintained whenever possible, but motorists should expect periodic delays. The bridge remains open to both vehicles and pedestrians at this time. Please use caution when traveling through the work zone and follow all posted signs and the direction of flaggers.
For more information about this project, please visit LebanonNH.gov/DryBridge.
Construction of the access road to pavement subgrade is complete, and preparation of the Route 12A subgrade is complete (south approach roadway widened area). Utility relocations are ongoing and will continue for several weeks.
During the week of May 25, 2026, construction crews will continue sewer work and retaining wall work at the Seminary Hill intersection.
As a reminder, while road work continues, construction crews and vehicles will be present in the area. Two-way traffic will be maintained whenever possible, but motorists should expect periodic delays. The bridge remains open to both vehicles and pedestrians at this time. Please use caution when traveling through the work zone and follow all posted signs and the direction of flaggers.
For more information about this project, please visit LebanonNH.gov/DryBridge.