West Lebanon, NH: South Main Street Dry Bridge Project Update

West Lebanon, NH:  South Main Street Dry Bridge Project Update

The contractor plans to mobilize to the site on Monday, March 16, 2026.  They are currently finalizing required City and State permits/notifications for the planned work, which includes demolition of the buildings located at 11 South Main Street and 18 South Main Street, site clearing, and earthwork.

Two-way traffic is expected to be maintained throughout this portion of the project; however, motorists should anticipate delays during certain phases of the work.  Please use caution when traveling through the work zone and follow all posted signs and directions from flaggers.

The anticipated bridge closure is still expected around September 2026.  The DPW will continue to provide updates as more information becomes available.

For more information about this project, please visit LebanonNH.gov/DryBridge.